Project Settings - Travel Rate
Reduce By Travel Rate for Labor
About Reduce Labor Hourly Rate by %
Feature
You can set this to reduce the labor rate by a percentage
Example - Published Labor Rate for Project Manager is $90.00
Per Hour
You need to bill this at $45.00 per hour - You would Enter
50.00 (50.00%) in the box (see image below)
In order to APPLY the Travel Rate Rule - This is done by
checking the box on the Labor Input Dialog (see image below)
See Example Below on how this should look in Estimate Summary
Related Articles
Travel Rate Settings
Project Settings - Travel Rate - Reduce Labor Rate By About Reduce Labor Hourly Rate by % Feature You can set this to reduce the labor rate by a percentage Example - Published Labor Rate for Project Manager is $90.00 Per Hour You need to bill this ...
Project Settings - Pro Rate and Duplication Rule
Pro Rate and Duplication Rule About Pro Rate Feature Pro Rate Feature Defined - Program will automatically Pro Rate all Associated Fees based on an 8 Hour Day Example - Daily Rate for Truck is $50.00 Labor works 4 hours - Program Bills $25.00 If ...
Project Settings - Project Cost Setup
Project Cost Set Up - Showing Two Options for Materials | Equipment | Specialty Items Project Cost can be set up with cost and percentages. The Best way is to Export Price List to Excel and then Import it back into the program to convert to the ...
Project Settings - Hotels / Lodging
Setting Up Hotels and Lodging To Open the Hotel and Lodging Table, Open the Project Settings dialog, then click on Open Hotel / Lodging Set Up Dialog (See Below) To Add Hotels Click "ADD" to Open Hotel / Lodging Set up Dialog (see image below) To ...
Project Settings - Small Tools
Small Tools Setting Up Small Tools Small Tools is a common billed item in Time and Materials - Calculated as a Associated Labor Fee Be sure to understand how is the used and billed (see image below) The most commonly used Small Tools is ...