Project Settings - Change Input Attributes
Change Input Attributes
To Access Input Attributes
- Open the Project Settings Dialog
- Click on Open / Modify Input Attributes
- The program allows the ability to change certain attribute names for the input.
To Change the Input Attribute
Open Attribute Dialog
You have (7) Default Associated Fee headers that can be changed.
You have (6) Allocation Headers that can be changed.
- Make your change and click ENTER and CLOSE
On the Project Settings Dialog, click ENTER to set the changes
You New Input Attributes should now show
Important Note: You do not have to change any input attribute if you do not want to.
Example of Modified Input Attributes
Related Articles
Change Input Attributes
Project Settings - Open / Modify Input Attributes User can Modify Input Attributes as shown below When you change an Input Attribute and click ENTER then all items related to that Input Attribute will be changed to the new Input Attribute. This ...
Project Settings - Change Invoice Attributes
Project Settings - Open / Modify Estimate Attributes User can Modify Estimate Attributes as shown below When you change an Estimate Attribute and click ENTER, then all items related to that Estimate Attribute will be changed to the new Estimate ...
Change Invoice Attributes
Project Settings - Open / Modify Invoice Attributes User can Modify Invoice Attributes as shown below When you change an Invoice Attribute and click ENTER then all items related to that Invoice Attribute will be changed to the new Invoice Attribute. ...
Project Settings - Overtime Rules and Settings
Overtime Rules and Settings Below is the Overtime Settings Dialog How to Set OT Settings for the 8 Hour 7 Day Overtime Rule This setting will bill OT as Follows - First 8 Hours Daily will be Billed at Regular Hourly Rate - 7 Days Per Week (Monday - ...
Project Settings - Vehicles and Mileage
Project Settings - Vehicles and Mileage Vehicles and Mileage can be billed from the Labor Input Dialog - You must first setup the Vehicles and Mileage (see below) Below is found in the Project Settings Dialog To Add Vehicles and Mileage Open Vehicles ...