Project Settings - Travel Rate - Reduce Labor Rate By

About Reduce Labor Hourly Rate by % Feature
  • You can set this to reduce the labor rate by a percentage 

  • Example - Published Labor Rate for Project Manager is $90.00 Per Hour 

  • You need to bill this at $45.00 per hour - You would Enter 50.00 (50.00%) in the box (see image below)


See Example Below on how this should be Entered 

In order to APPLY the Travel Rate Rule - This is done by checking the box on the Labor Input Dialog (see image below)

  • First Entry is for Travel Time - See Work Description and Hourly Rate - It is reduced by 50% 

  • Second Entry is for Work Time - See Work Description and Hourly Rate which is now Full Rate 




    • Related Articles

    • Project Settings - Travel Rate

      Reduce By Travel Rate for Labor  About Reduce Labor Hourly Rate by % Feature You can set this to reduce the labor rate by a percentage Example - Published Labor Rate for Project Manager is $90.00 Per Hour You need to bill this at $45.00 per hour - ...
    • Project Settings - Pro Rate and Duplication Rule

      Pro Rate and Duplication Rule About Pro Rate Feature Pro Rate Feature Defined - Program will automatically Pro Rate all Associated Fees based on an 8 Hour Day Example - Daily Rate for Truck is $50.00 Labor works 4 hours - Program Bills $25.00 If ...
    • Pro Rate and Duplication Rule

      Project Settings - Pro-Rate and Duplication Rule About Pro-Rate Feature Pro-Rate Feature Defined - Program will automatically Pro Rate all Associated Fees based on an 8 Hour Day  Example - Daily Rate for Truck is $50.00 Labor works 4 hours - Program ...
    • Project Settings - Overtime Rules and Settings

      Overtime Rules and Settings Below is the Overtime Settings Dialog How to Set OT Settings for the 8 Hour 7 Day Overtime Rule This setting will bill OT as Follows - First 8 Hours Daily will be Billed at Regular Hourly Rate - 7 Days Per Week (Monday - ...
    • Project Settings - Small Tools

      Small Tools Setting Up Small Tools Small Tools is a common billed item in Time and Materials - Calculated as a Associated Labor Fee  Be sure to understand how is the used and billed (see image below) The most commonly used Small Tools is ...